The Transmission Company of Nigeria and the Kano State Government have reached an agreement to resolve a protracted legal dispute that had stalled the completion of the Kumbotso–Rimin Zakara 330kV transmission line.

The resolution followed a high-level meeting convened on July 21, 2025, by the Kano State Ministry of Land and Physical Planning to address issues relating to land ownership and compensation, which had led to litigation and delayed the project.

In a statement issued today by the General Manager, Public Affairs at TCN, Ndidi Mbah, confirmed that under the new agreement, the state government would compensate affected individuals whose cases remain in court and provide alternative land for others.

She expressed optimism that with the legal issues out of the way, work on the transmission line would progress swiftly.